Glass partition brandInstallation construction process key points

(1) Mark vertical lines on the wall according to the design size, and mark the position of the partition on the ground and ceiling.

(2) Make the lower part (covering panel, board or brick) on the marked position line according to the drawing requirements, and anchor it to the structure at both ends (brick wall or column).

(3) Complete the installation of the upper part of the partition. The installation sequence is:

① Check whether the wooden bricks on the brick wall are buried according to the regulations;

② Stand the reinforcing bars against the wall according to the marked position line, and nail them firmly to the wooden bricks on the wall;

③ Nail the upper and lower rafters and middle purlins.


Construction conditions. The basic surface has been completed and checked for acceptance, and there is a certain operating space on site. The scaffolding has been erected, or there are high stools and footboards. All decoration materials have been prepared and stacked nearby . The electrical wiring has been introduced, and the equipment is ready.