ActivityGlass partitionConstruction process:
1. Observe the overall construction environment of the activity glass partition, carefully observe the surrounding environment to survey the main work of the construction environment, and survey the main purpose of the construction environment where the partition is to be installed is to determine whether the site has the installation conditions, and precisely record the location of the beams and columns on the roof and the reserved space position, as well as the location of the air conditioning pipeline system, to customize the construction plan; the suitable construction time is when there is no decoration in the site.
2. According to the measurement and positioning, according to the requirements of the construction drawings, control lines for the position of the activity partition are placed on the indoor floor, and the position line of the partition wall is led to the side wall and ceiling; when the line is struck again, the installation position line of the fixing part should be struck out; the installation height of the track must be discussed with the construction team to install the ceiling, otherwise it will cause many unnecessary troubles.
3. The installation of steel structures and track fittings. The steel structure is a load-bearing structure connecting the ceiling and track. The safety of the entire activity glass partition system is involved, so it must not be taken lightly; according to the construction drawings, drill and blow screws on the roof, and then weld and fix the angle iron; select the track fixing parts according to the design requirements; consider the wall, ground, and ceiling closure method before installing the track, which is convenient for the installation of the activity partition wall. Calculate the weight of the activity partition wall to determine the load-bearing capacity of the track and the specifications and fixing methods of the embedded parts. The embedded parts of the track installation must be firm, and the track should be fixed firmly to the main structure. All metal parts should be rust-proof treated.

4. Install the track:
(1) Suspension track: The fixing method of the suspension guide is to install pulleys on the top surface of the partition and connect them with the upper suspension track. The track and pulley should be selected according to the size of the load. For lightweight activity partition walls, the track is fixed with wood screws or counter-twisted screws on the top wood frame or steel frame. For heavy-duty activity partition walls, the track is fixed with counter-twisted screws or welding on the steel frame.
(2) Support track: The fixing method of the supporting guide is that the pulley is at the bottom of the partition and constitutes the lower support point with the ground track. The track is fixed with expansion bolts or embedded parts, and the guide rail is installed on the top wood frame.
(3) When installing the track, according to the specific situation of the track, install the pulley in advance or reserve an opening for the track (usually 1/2 partition next to the wall).
5. Install the activity panel: According to the installation method, accurately mark the pulley baseline on each panel, and then fix the pulley bracket with screws on the upper or lower horizontal of the partition; then install the panels one by one into the track, adjust each panel to be vertical to the ground, and flexible in push-pull rotation, and then carry out the connection and fixing of each partition. Hinges are usually used to connect adjacent panels.
6. Decoration: According to the requirements of the interior design of the home, decorate with soft packages, cold-mounted solid wood boards, decorative panels, or glass inlays; after the decoration is done, paint or finish the edges. The decoration construction should be carried out according to the corresponding standards and the choice of home decoration style.
7. Debugging: After the activity panel is installed, fine-tune the panel height, sealing, and other details, clean up the site after debugging, and complete the installation work.